Skip to main content
Microsoft Project logo

Product

AEC Integrations maintained

Microsoft Project

No reviews yet

About

Microsoft Project is Microsoft's project scheduling software, sold as the Project desktop application and as Project for the web inside Microsoft 365 and Planner. Teams build task lists, dependencies and Gantt charts, assign resources and track progress against a baseline. Construction schedulers use the desktop version for CPM schedules on smaller projects and exchange its MPP and XML files with Primavera P6, Procore and lookahead planning tools.

How teams use it

By audience

Construction Management
  • Builds CPM construction schedules with task dependencies, durations, and critical-path identification to drive the master program
  • Develops resource-loaded Gantt charts to plan crews, equipment, and material deliveries against the timeline
  • Sets and tracks baseline schedules, then measures actual progress and slippage against planned dates
  • Manages milestone gates (permits, inspections, substantial completion) and float to keep the project on track
  • Produces lookahead and progress reports for project controls and schedule-of-values coordination
General Contracting
  • Maintains the master project schedule and rolls up subcontractor activities into a single CPM network
  • Coordinates trade sequencing and handoffs by linking predecessor/successor tasks across packages
  • Runs what-if and delay analyses on the critical path to evaluate acceleration or recovery options
  • Allocates labor and equipment resources, leveling overallocations across concurrent activities
  • Tracks percent-complete and updates the schedule for owner and lender progress reporting
Owner/Developer
  • Reviews the contractor's baseline Gantt schedule and milestone dates to validate the delivery timeline
  • Monitors progress against baseline to flag delays affecting occupancy, financing, or lease commitments
  • Models phasing and milestone dependencies across multi-building or multi-phase developments
  • Uses schedule data to align design, procurement, and construction milestones in the overall program

By phase

Pre-Construction
  • Builds the initial CPM baseline schedule and Gantt chart from the WBS during planning and bid
  • Sequences design, permitting, procurement, and long-lead material activities with dependencies
  • Defines milestones (NTP, mobilization, permit approvals) and float to set realistic completion dates
  • Resource-loads the plan to forecast crew, equipment, and budget needs before mobilization
  • Runs schedule scenarios to evaluate phasing options and constructability before construction starts
Construction
  • Updates actual start/finish and percent-complete against the baseline to track on-site progress
  • Recalculates the critical path as field conditions change to identify and mitigate schedule slippage
  • Generates weekly/three-week lookahead schedules to coordinate trades and deliveries
  • Levels resources and reschedules to manage overallocations and concurrent activity conflicts
  • Documents delays and produces progress reports for owner, lender, and claims support

Integrations (22)

Integrates with Details
AcuiteDirection:OutboundNative1 type of data
ALICE ModelDirection:InboundNative1 type of data
ALICE OptimizeDirection:BothNative1 type of data
Autodesk Forma BuildDirection:OutboundNative1 type of data
Birdview PSADirection:BothNative1 type of data
BuildotsDirection:BothNative1 type of data
ConstructivIQDirection:OutboundNative1 type of data
Deltek VantagepointDirection:BothNative1 type of data
FieldwireDirection:OutboundNative1 type of data
HeavyJobDirection:Inbound1 type of data
KraneDirection:OutboundNative1 type of data
Kroo ConnectorDirection:OutboundiPaaS
NavisworksDirection:OutboundNative1 type of data
Octave Sequence EnterpriseDirection:OutboundNative1 type of data
OpenSpaceDirection:OutboundNative1 type of data
Oracle Primavera CloudDirection:BothNative1 type of data
Oracle Primavera P6Direction:Both1 type of data
Power AutomateDirection:BothiPaaS2 types of data
Premier Construction SoftwareDirection:BothNative1 type of data
Procore Project ManagementDirection:OutboundNative1 type of data
SmartappDirection:BothNative1 type of data
SmartsheetDirection:BothNative1 type of data

6 more pairs reachable via connectors

Only partners listed on AEC Integrations appear here. If one is missing, suggest a correction.

No reviews yet — be the first to review this product.

Directory updates

Know when new tools and reviews land

AEC Integrations is live and still growing. Add your email for occasional updates as we expand the directory with new tools, integrations, and reviews.